Managing cost overruns
A capital project has gone over budget. Which tool actually fixes that, and which one just papers over it.
A cost overrun does not have one fix. Contingency is the buffer the board already planned for uncertainty in the current scope; once it runs out, a change order is the documented mechanism for costs that fall outside the original scope, price, or schedule. There is no separate overrun-management process beyond these two tools.
Where an overrun actually comes from
Two very different things get lumped together as "we went over budget." One is a cost the estimate already flagged as uncertain, a site condition not yet exposed, a material price that moved before the contract was signed. The other is a cost nobody scoped at all, an owner-requested upgrade, a code requirement discovered at permitting, a hidden defect found once demolition starts.
The first belongs to contingency. The second belongs to a change order. Treating both the same way, as one undifferentiated "the budget went over," hides which lever actually failed and makes it harder to explain to owners what happened.
Contingency: the buffer you already planned
Contingency is money set aside for uncertainty that is already known to exist in the current scope, even though its exact size or timing is not yet known. It is not a fixed percentage of the budget. How much a project carries depends on how developed the estimate is and how risky the project is, and that range narrows as design detail firms up.
"An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain."
Source: Recommended Practice 40R-08, Contingency Estimating, General Principles, AACE International
See Contingencies for how a board sizes and tracks this line.
Change order: the mechanism for everything else
Once a cost falls outside the scope the contract describes, contingency is the wrong tool, even if money is still sitting in that line. The contract mechanism for a scope, price, or schedule change is a change order, and it applies the same way whether the change is an unforeseen condition the contractor discovered or an upgrade the board chose to add midproject.
"An official change of any kind in the original scope of work or terms of a construction contract agreed to by the owner, contractor, and project designer."
Source: Change Orders, Associated General Contractors of America
See Change orders for how one gets written, priced, and approved.
When both run out
If contingency is spent and change orders keep arriving, that is a funding decision, not a construction one. Boards typically fund a shortfall the same three ways they funded the original project: reserves, a special assessment, or a loan.
Whether the board can approve additional funding on its own, or has to bring it to a member vote, varies by state and by your governing documents. Check your CC&Rs, bylaws, and state statute before assuming the board can act alone.
See Project budgeting, Funding projects, and Special assessments.
Check yourself
Answer before you read the explanation, recalling it is what makes it stick.
The project's engineer finds a rotted structural beam behind a wall that wasn't visible before demolition. This wasn't in the original scope. What absorbs this cost?
The contingency line in the budget is fully spent, and the contractor identifies another unforeseen repair. What happens next?
Midproject, the board approves nicer fixtures than originally specified, a discretionary upgrade with no defect behind it. How should this cost be treated?
Sources
- Recommended Practice 40R-08, Contingency Estimating, General Principles, AACE International
- Change Orders, Associated General Contractors of America
- How can my association fund an HOA capital improvement, FirstService Residential
Related elsewhere in the Academy
Capital Projects
Next, see exactly how a change order gets written and priced: Change orders.
How much contingency a project carries, and who on the board is authorized to approve a change order or additional funding beyond the original budget, vary by project and by your association's own governing documents.